INDUSTRY
Financial Services (Insurance)
CHALLENGE
DR&P Group required a trusted IT partner to manage the complete technology aspect of its office relocation. With a tight project timescale and more than 50 employees moving into a new office, the objective was to ensure business operations could continue with minimal disruption while delivering a modern, fully connected working environment.
RESULTS
The relocation was successfully delivered within the agreed timescales, providing DR&P Group with a modern, secure and fully connected workspace. Employees were able to settle into the new office quickly, with the infrastructure and support needed to continue working from day one.
KEY PRODUCT
DR&P relies on us to support its entire technology estate across approximately 35–40 locations.
Our partnership includes:
- Managed IT Services
- Microsoft Modern Workplace
- Business Broadband
- Business Telephony
- Network & Connectivity Solutions
With an established relationship already in place, DR&P trusted MCS Group to manage every aspect of the IT relocation to its new headquarters.
-
50+
Employees relocated
-
3-4 days
To complete office move
-
35-40
Locations supported across the business
"MCS Group once again exceeded our expectations. Our office relocation involved far more than simply moving premises, requiring detailed planning and the successful delivery of new internet services, networking, Wi-Fi, firewalls, conferencing solutions and workstation deployments. The phased migration ensured minimal disruption to the business, while the MCS Group engineers worked seamlessly alongside our team throughout. A huge thank you to the entire team, especially James and Rhys, for their professionalism, dedication and outstanding support."
Craig Prunty
Group Head of IT | DR&P
DR&P Group's Story
Founded in 1977, David Roberts & Partners (DR&P Group) is one of the UK's leading independent insurance brokers. With more than 550 colleagues across 34 UK offices and five international locations, DR&P provides tailored insurance and risk management solutions to businesses of all sizes.
DR&P manages over £620 million in gross written premium (GWP) on behalf of its clients. The company continues to expand through a strategic mix of acquisitions and organic growth, solidifying its position as an industry leader.
The Challenge
As part of its continued growth, DR&P Group decided to relocate to a larger, more modern office that would provide an improved working environment for its employees. The project presented a significant logistical challenge. Within just three weeks, the entire relocation had to be planned, coordinated and delivered, with the physical move taking place over three to four days.
-
More than 50 employees required new workstations to be installed and configured within a three-week project timeline.
-
The deployment of three fully equipped meeting rooms complete with wall-mounted displays and video conferencing technology.
-
Ensure every employee could begin working immediately in the new office.
- Minimise disruption to business operations throughout the move.
The Solution
Working closely with DR&P throughout the planning phase, MCS Group developed a structured project plan to ensure every aspect of the relocation was delivered efficiently. Over the course of the move, multiple engineers were onsite to oversee the installation, configuration and testing of the new IT environment. Every workstation was installed and prepared ready for users, while meeting rooms were equipped with wall-mounted displays and conferencing cameras to support collaboration from the moment the office opened.
- Complete network infrastructure, including business broadband, Wi-Fi deployment and a SonicWall firewall to provide secure connectivity throughout the new premises.
-
All network cabling was correctly patched and tested, equipment was fully configured before staff arrived, and engineers remained onsite to resolve any teething issues immediately.
-
Multiple engineers onsite throughout the move to support users and resolve any issues immediately.
-
Assisted employees in settling into their new workspaces, ensuring every device was operational and ready for use.
The Results
Business Ready from Day One
Every workstation, meeting room and network connection was fully configured, allowing employees to begin working immediately in their new office.
Minimal Business Disruption
Detailed planning and onsite engineering support helped ensure the relocation was completed smoothly within a tight three-week project timescale.
Complete IT Infrastructure Delivered
From broadband and Wi-Fi to telephony, network security and meeting room technology, every element of the IT environment was delivered as part of one coordinated project.
Improved Collaboration
Three new meeting rooms equipped with modern conferencing technology have created better spaces for internal collaboration and client meetings.
Secure & Reliable Connectivity
A new network, business broadband, Wi-Fi infrastructure and SonicWall firewall provided secure, high-performance connectivity across the office from day one.
A Trusted Technology Partner
Having supported DRP Group for over six years, MCS Group was able to deliver the relocation with confidence, providing the expertise and reassurance needed for a successful transition.